Task completion (Done) after status change (Done)

We’ll show you how to set up a CA that automatically changes a task’s status to Done when it is moved to the final stage of work

Uspacy Support Team avatar
Written by Uspacy Support Team
Updated this week

By configuring a conditional action, you can automatically update a task’s status to Done as soon as its stage changes to Done. This is useful when work is considered finished after a certain stage, eliminating the need to manually update the status. Automation helps prevent missed tasks and keeps your processes organized

Step-by-step setup below ⬇️

Setting up the Conditional Action

Select the trigger. In our example, it’s a task change.

Set the condition. Specify the group whose tasks will trigger the automation.

.

Select the stage the task must move to in order for the automation to run.

💡 Both conditions must be met at the same time. The conditional action won’t work if you move a task from that group to any other stage.

Select Change fields as an action.

Select Task as the entity whose fields need to be changed.

Add the Status field and set it to Done.

Once everything is configured, click Create.

Result

Move a task from the specified group to the designated stage.

You’ll see that its status is automatically updated to Done

If you have additional questions or you need to contact the support, send a request to this email [email protected]